The Himamaylan City government has sent a final demand letter to contractors over delays in seven infrastructure projects worth a combined P398.395 million flagged by the Commission on Audit (COA), warning of possible sanctions for continued non-compliance.
In a statement on Thursday, November 19, Mayor Rogelio Raymund I. Tongson Jr. said the city had already sent the final demand to the concerned contractors following discussions during the COA exit conference.
Further action, including the possible imposition of sanctions under Republic Act 9184, or the Government Procurement Reform Act, would follow as warranted, he said.
The move comes after COA flagged seven unfinished infrastructure projects funded through the city’s loan, which incurred delays ranging from 603 to 1,286 days beyond their original completion schedules as of December 31, 2025.
The seven projects had a combined contract cost of P398.395 million and were awarded to three contractors, including MKU Construction and Supply, Wilkinson Construction, and the Almana Construction Development Corporation, which secured the largest share, totaling P282.48 million.
The Promenade reclamation project recorded the longest delay at 1,286 days, followed by the Aguisan River desilting and slope protection project at 1,173 days and the Sara-et coastal protection project at 1,167 days.
Other projects included the Caradio-an River desilting and slope protection works, delayed by 1,160 days; the Barangay 2 boulevard development, 1,065 days; the Barangay 1 boulevard development, 1,048 days; and the socialized housing project in Barangay III-Poblacion, 603 days.
In its audit observations, COA raised concerns over inadequate project monitoring and the city’s failure to impose appropriate sanctions against contractors despite the delays.
The finding raised questions over the implementation of the city’s loan-funded infrastructure program, particularly the monitoring of contractors and the use of borrowed public funds.
In response, Tongson said concerned department heads attended the COA exit conference, where the audit observations were discussed, and subsequently submitted the required action plan.
He said several recommendations had already been acted upon, while measures addressing the remaining observations were still ongoing.
The city, however, could not provide the detailed action plan submitted to the state auditor.
Not yet totally paid
Tongson clarified that delays or incomplete project components did not automatically mean that the entire contract amount had already been paid.
He said the city follows a progress-billing arrangement, under which payments are released only for completed work that has been duly validated.
The remaining project phases, he added, are covered by approved but still unavailable bank loans, which may only be disbursed after the corresponding work has been completed and verified.
The projects were part of the city’s broader borrowing program authorized under Ordinance No. 2020-024A, which allowed the local government to secure up to P470 million in loans from the Land Bank of the Philippines.
Of the authorized amount, P304.91 million was allocated for infrastructure and development projects, while P165.09 million was intended for heavy equipment acquisitions.
The sinking of people’s money?
The equipment allocation included two amphibious cutter-suction dredgers worth P142.8 million.
Tongson said that he already ordered the City Legal Office (CLO) to investigate the reported sinking of the city’s dredger and submit its findings to his office for appropriate action.
The directive follows earlier reports of the sinking of city-owned dredging equipment, which raised questions about the status and use of equipment acquired under the city’s borrowing program.
Because the probe is ongoing, the mayor’s statement did not disclose the circumstances of the reported sinking or clarify whether the dredger was one of the two amphibious dredgers covered by the equipment allocation.
Tongson maintained that all projects covered by the audit observations were existing and duly documented, and that no payments had been released beyond the value of work actually accomplished.
He also claimed that other projects had since reached higher levels of completion and remained under close monitoring.
The actual amount paid to the contractors, the remaining project balances, and the status of the delayed works also remain important matters for public accountability, which the chief executive’s statement did not dare to address.
Brigada News FM Philippines has yet to seek comment from the three contractors on when they can finish the long-delayed projects, after the city sent them demand letters.
Moreover, the city has also yet to clarify and explain the geohazard posed by the delayed socialized housing project, which is situated on top of the West Negros Fault (WNF), one of the 10 fault lines on the island that could potentially generate a 6.9-magnitude earthquake.*